§ 88-518-05. REVIEW AND ACTION  


Latest version.
  • 88-518-05-A. The city plan commission must review each complete application for project plan approval and take one of the following actions:

    1.

    approve the application;

    2.

    identify those revisions or modifications that would allow approval of the application;

    3.

    approve the application with conditions;

    4.

    disapprove the application; or

    5.

    forward the application to the board of zoning adjustment for review and action.