§ 19-85. Liquidated damages.
Liquidated damages for nonperformance during the construction of a system, or the upgrade of a system, shall be chargeable as follows:
(1)
For failure to submit required plans regarding the construction of a system or the upgrade, per day ..... $ 100.00
(2)
For failure to commence the construction of a system or the upgrade of a system in accordance with the requirements of this chapter or a separate franchise agreement, per day ..... 100.00
(3)
For failure to complete the construction of a system or the upgrade of a system in accordance with the requirements of this chapter or a separate franchise agreement, per day ..... 1,000.00
(Ord. No. 930358, § 1(43.85), 8-25-94)